Construction of the Decorah Community School District’s new elementary school remains on schedule, with crews having installed precast concrete wall panels and received the first structural steel components at the site. The project will replace John Cline Elementary School and is scheduled to open for the 2027-28 school year.

The update, issued July 30, 2026, comes as the district continues to await final approval of the project plans from the Iowa State Fire Marshal’s Office. District officials said they do not currently anticipate that review affecting the overall construction schedule.

Construction moves into vertical work

Voters approved the new school project in November 2024. Early site work and utility relocations were completed in the spring, followed by installation of rammed aggregate piers ahead of schedule and a community groundbreaking celebration in May.

During June, construction crews completed the building’s footings and foundations. In July, the project reached its latest milestone when precast wall panels were erected and the first structural steel components arrived, giving residents a clearer view of the future facility.

The district described the work as significant progress toward a new learning environment for Decorah students and families.

State review focuses on building use

Project plans were submitted to the Iowa State Fire Marshal’s Office in January 2026. Since then, the district’s architects, Emergent Architecture, have remained in communication with the state agency during the review.

According to the district, the remaining questions do not concern the building’s structural integrity, safety or overall design. Instead, the discussions involve occupancy and operational considerations, including how particular spaces will be used so the appropriate life-safety requirements can be applied.

Emergent Architecture is providing additional information and discussing possible solutions with the State Fire Marshal’s Office. The firm is confident the remaining items can be resolved through continued collaboration and clarification of the building’s intended use.

“We appreciate the ongoing communication with the State Fire Marshal’s Office as they work to fully understand how the building will function and how each space will be used,” Tim Cronin, Decorah superintendent, said.

Cronin said the district looks forward to completing the approval process and moving the project forward.

City and project partners monitoring schedule

The City of Decorah has worked with the school district, design team and construction team to determine how work can proceed safely while the state review continues. Project partners said any additional modifications required by the review could be accommodated without affecting work that has already been completed.

“We appreciate the community’s continued support and patience as we work through this process,” Cronin said. “The progress taking place on site is exciting to see, and we remain focused on delivering a state-of-the-art learning environment for the students and families of Decorah.”

The district said it will share additional updates as information becomes available on its project website, decorahelementaryupdates.org.